What happens during a commercial rooftop solar install?

By Nate Hadachek, CEO, Impact Energy & RoofingPart of Commercial

On site it runs in three stages, racking and panels go on the roof, conduit is run down the building to the electrical room, and then the building department inspects and the utility approves the connection. Before any of that come design, permits and the utility application, which usually take longer than the install itself.

Three stages happen at the building: racking and panels on the roof, conduit down the building, and inspection plus utility approval at the end. We'll walk through each one using a Denver-metro office building we installed in July 2026, a flat roof with downtown on the horizon. The middle stage is the one owners don't expect.

What happens before anyone gets on the roof?

Paperwork, and plenty of it. After the site walk and a signed proposal, the project needs:

  • A final design. Panel layout, racking, wiring, the path to the electrical room and the tie-in point.
  • A building permit from the city or county.
  • A utility interconnection application. In Xcel Energy's Colorado territory, the application goes through the utility's online portal and moves through program, completeness and engineering reviews. Larger or more complex systems can need further study. 1

This is often the longest part of the project, and most of it is waiting on reviews. We handle the filings and keep you posted.

Stage one: what goes on the roof?

Racking first. On a flat commercial roof, racking sets the panels at an angle toward the sun and keeps rows evenly spaced. Depending on the roof and the design, racking is held by weight, by attachments into the structure, or both. Every attachment through the roof membrane gets flashed and sealed.

Then panels. Panels clip onto the racking, row by row, and are wired together in groups. The layout keeps open paths for fire access and for servicing the array and any rooftop equipment.

Materials go up by lift or crane. Panels and racking are staged in the parking lot or alley and lifted to the roof. Expect part of the lot to be used for staging during this stage.

If the roof is near the end of its life, this is the moment you will wish you had replaced it first. We look at that before the proposal, and our commercial roofing work can happen on the same schedule.

Stage two: how does power get from the roof to the electrical room?

Through conduit, the metal pipe that protects the wiring. On a one-story building it can be a short run. On a four-story office building like our Denver-metro job, the wiring had to get from the roof to the electrical room on a lower floor, and the cleanest path was down the outside wall. That meant a lift on the side of the building and a crew mounting conduit floor by floor.

This stage surprises owners because it happens at eye level. People walking in see a lift and a crew on the wall. We plan the lift's position around entrances, parking and tenants, and tell you ahead of time which days it will be there.

At the bottom, the conduit enters the electrical room, where the inverters or the connection equipment tie the system into the building's electrical service. Grid-connected inverters are built to the UL 1741 standard and follow IEEE 1547 rules for how they connect to and disconnect from the grid. 2 3 The final tie-in usually needs a planned power shutdown, scheduled with you.

Stage three: inspection and utility approval

When the install is done, the building department inspects the electrical work. After it passes, the inspection and closeout documents go to the utility. 1 The utility then handles the meter, and once the meter work is done, it issues permission to operate. 1 The system stays off until then.

How long does a commercial project take?

It depends on the size, the building and the utility. The general pattern holds on most jobs: design, permits and the utility application take longer than the install, and the time between the final inspection and permission to operate depends on the utility's schedule. You get our expected sequence in the written proposal, and we update you as each review clears.

What should you plan for as the owner?

  • Lift and material staging in the lot or alley for part of the job.
  • A planned power shutdown for the tie-in.
  • Access to the roof and the electrical room.
  • Signatures the utility and the city need from the owner.
  • Telling tenants or staff about the lift days.

For where else a business can put panels, read where can a business put solar. If a building already has solar from an installer that has closed, see my solar installer went out of business. If you want to understand the equipment once it is installed, what is all the solar equipment on my garage wall explains inverters and junction boxes in home terms.

Save this

  • Before the install: design, permit and utility application.
  • Stage one: racking, then panels, with every roof attachment flashed.
  • Stage two: conduit from the roof to the electrical room, often by lift on the outside wall.
  • Stage three: city inspection, utility meter work, permission to operate.
  • The paperwork usually takes longer than the install.
  • Plan for staging space, a lift and one planned shutdown.

To plan a roof and an array together, start at our commercial hub or commercial solar.

Questions

Will my building lose power during the solar install?

Most of the work happens without touching your power. The final tie-in to the electrical service usually needs a planned shutdown, which we schedule with you ahead of time at an hour that works for your business.

Why is there a lift on the outside of the building?

To run conduit from the roof down to the electrical room. On a multi-story building, the outside wall is often the cleanest path, and a lift lets the crew mount the conduit safely floor by floor.

What is permission to operate?

It is the utility's sign-off that your system can start sending power. It comes after the final inspection and the meter work, and the system stays off until you have it.

Can businesses stay open during a commercial solar install?

Usually, yes. Most of the work is on the roof. We plan where the lift and materials go, keep walkways clear, and tell you which days will be noisy or need part of the parking lot.

Sources

  1. [1]Interconnection Application Portal Process Guide (Colorado DER interconnection). Xcel Energy
  2. [2]IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces (IEEE 1547-2018). IEEE Standards Association
  3. [3]UL 1741: Inverters, Converters, Controllers and Interconnection System Equipment for Use With Distributed Energy Resources. UL Standards & Engagement
Get an estimate

Tell us about the roof, the panels or the building.

Send the form or call. We set up an assessment, then send a written proposal with the scope and the price.

Monday–Friday 9 a.m.–5 p.m.

General information about roofing and solar in Colorado, not legal, tax or insurance advice.

Answers on this site are general information about roofing and solar in Colorado, not legal, tax or insurance advice. Programs, codes and utility rules change; your written proposal and your insurer or utility have the final word.